Andhra Pradesh Strengthens Port Network as Four Projects Advance — Yet Scale Debate Persists
Maritime News, New Delhi / Amaravati, Andhra Pradesh, India: Andhra Pradesh continues to deepen its port-led growth strategy, with four ports currently under construction even as the Union Government outlines a broader national push toward maritime modernization.
In a written reply to the Lok Sabha, Union Minister for Ports, Shipping and Waterways Sarbananda Sonowal detailed the status of port development nationwide, noting 12 operational Major Ports under central control and 68 operational Other Than Major Ports (OTMPs) managed by states. Two additional ports — Vadhavan in Maharashtra and Galathea Bay in the Andaman & Nicobar Islands — have recently been notified as Major Ports, underscoring the Centre’s focus on long-term capacity creation.
Within Andhra Pradesh, four port projects are presently under development:
- Mulapeta Port (formerly Bhavanapadu), Srikakulam District
- Machilipatnam Port, Krishna District
- Ramayapatnam Port, SPSR Nellore District
- Kakinada SEZ Port, Kakinada District
The state already hosts significant operational ports including Visakhapatnam (a Major Port), Krishnapatnam, Gangavaram, Kakinada Anchorage and Kakinada Seaports. The addition of new facilities is aimed at reinforcing Andhra Pradesh’s position as a leading maritime gateway on India’s eastern seaboard.
Modernisation Push: Efficiency Gains or Incremental Upgrades?
The Government highlighted ongoing modernization efforts across Indian ports, including mechanisation of berths, digitalisation, capital dredging to accommodate larger vessels, and improved multimodal connectivity through road, rail, and waterways.
Operational reforms such as RFID-based gate automation, container scanners, direct port delivery systems, e-documentation, and the Maritime Single Window (SagarSetu 2.0) have been introduced to reduce vessel turnaround time and improve efficiency.
However, maritime analysts caution that digitisation and procedural reforms, while necessary, do not automatically translate into throughput growth unless backed by cargo generation, industrial hinterland development, and private investment confidence.
The real test for Andhra Pradesh’s new ports will lie in attracting sustained cargo flows rather than merely expanding infrastructure footprint.
Sagarmala Support and Funding Realities
Under the Sagarmala programme, the Centre provides financial assistance across five pillars: Port Modernization, Port Connectivity, Port-Led Industrialization, Coastal Community Development, and Coastal Shipping & Inland Water Transport.
For Andhra Pradesh, one notable completed project under the Port Modernisation pillar includes the ₹73.34 crore improvement of Kakinada Anchorage Port infrastructure, supported with ₹36.67 crore in Sagarmala assistance.
While funding support is available, critics note that compared to western coastal states such as Gujarat and Maharashtra, Andhra Pradesh’s central funding allocations under modernization appear relatively modest in scale.
The broader concern remains whether project execution timelines and cargo alignment will match the state’s ambitious maritime aspirations.
Competing Coastlines, Competitive Pressure
With eastern India witnessing rising port activity in Odisha and West Bengal, and western India dominated by large-scale private and major ports, Andhra Pradesh faces increasing competitive pressure.
The state’s geographic advantage — proximity to Southeast Asia trade routes — offers strategic potential. Yet the multiplicity of ports under development could also risk capacity fragmentation unless integrated with industrial corridors and export-oriented manufacturing clusters.
Green and Cruise Ambitions
The Union Government has also launched parallel initiatives such as the HaritSagar green port guidelines, the Green Tug Transition Programme (GTTP), and the Cruise Bharat Mission.
While Andhra Pradesh has coastal tourism potential, including cruise development prospects, industry observers stress that cruise traffic depends heavily on international passenger flows and port-side tourism infrastructure — areas still evolving along the east coast.
Strategic Outlook
Andhra Pradesh has clearly positioned ports at the centre of its economic growth strategy. The construction of Mulapeta, Machilipatnam, Ramayapatnam and Kakinada SEZ Port signals expansion intent.
Yet as maritime economists point out, capacity addition must align with cargo ecosystems, logistics integration and sustained investor participation.
The coming years will determine whether Andhra Pradesh transitions from infrastructure expansion to maritime consolidation — transforming its coastline into a high-volume trade corridor or navigating the risks of overcapacity in an increasingly competitive port landscape.
Annexure- 1
The list of 12 Major Ports:
| Sl.No. | Name of Major Port | State |
| 1 | Syama Prasad Mookerjee Port Authority | West Bengal |
| 2 | Paradip Port Authority | Odisha |
| 3 | Visakhapatnam Port Authority | Andhra Pradesh |
| 4 | Chennai Port Authority | Tamil Nadu |
| 5 | Kamarajar Port Limited | |
| 6 | V.O. Chidambaranar Port Authority | |
| 7 | Cochin Port Authority | Kerala |
| 8 | New Mangalore Port Authority | Karnataka |
| 9 | Mormugao Port Authority | Goa |
| 10 | Mumbai Port Authority | Maharashtra |
| 11 | Jawaharlal Nehru Port Authority | |
| 12 | Deendayal Port Authority | Gujarat |
Annexure – 2
The list of 68 operational Other Than Major Ports (OTMPs):
| Sl. No. | Name of States / Ports | Sl. No. | Name of States / Ports |
| GUJARAT | GOA | ||
| 1 | Alang | 1 | Panaji |
| 2 | Bedi | KARNATAKA | |
| 3 | Bhavnagar | 1 | Karwar |
| 4 | Dahej | 2 | Old Mangalore |
| 5 | Jafarabad | ANDAMAN & NICOBAR | |
| 6 | Jakhau | 1 | Campbell Bay |
| 7 | Magdalla | 2 | Diglipur (Port Cornwalis) |
| 8 | MagdallaHazira Port (AHPPL) | 3 | SwarajDweep (Havelock) |
| 9 | Magdala Adani Hazira Port | 4 | Hut Bay |
| 10 | Navlakhi | 5 | Katchal (East Bay) |
| 11 | Okha | 6 | Malacca Car Nicobar (East) |
| 12 | Pipavav (GPPL) | 7 | Mayabunder |
| 13 | Porbandar | 8 | NancowryHarbour (Camotra) |
| 14 | Sikka | 9 | Shaheed Dweep (Neil Island) |
| 15 | MandaviMundra | 10 | Port Blair |
| 16 | MandaviMundra Port &SEZ | 11 | Rangat (ElephinstonHarbour) |
| 17 | Veraval | TAMIL NADU | |
| 18 | Salaya | 1 | Cuddalore |
| MAHARASHTRA | 2 | Ennore Minor Port | |
| 1 | Bankot | 3 | Kattupalli |
| 2 | Bhiwandi | 4 | Koodankulam |
| 3 | Dahanu | 5 | Thirukkadaiyur |
| 4 | Dabhol | 6 | Nagapattinam |
| 5 | Dharamtar (Alibag) | 7 | Udangudi |
| 6 | Jaigad | PUDUCHERRY | |
| 7 | Karanja | 1 | Karaikal |
| 8 | Rajpuri / Dighi | 2 | ChemplastSanmarKaraikal |
| 9 | Ratnagiri | 3 | Puducherry |
| 10 | Redi | ODISHA | |
| 11 | Revdanda | 1 | Gopalpur |
| 12 | Ulwa-Belapur (Panvel) | 2 | Dhamra |
| 13 | Vasai | KERALA | |
| 14 | Vijaydurg | 1 | Beypore |
| 15 | Belapur | 2 | Kollam |
| 16 | Yogayatan | 3 | Azhikkal |
| ANDHRA PRADESH | |||
| 1 | Kakinada Anchorage Port | ||
| 2 | Kakinada Seaports Port | ||
| 3 | Rawa | ||
| 4 | Krishnapatnam | ||
| 5 | Gangavaram |
Annexure – 3
The list of projects under Port Modernization pillar funded under Sagarmala scheme
| Sl.No. | Name of Project | State / UT | Project cost
(in ₹ crore) |
Assistance under Sagarmala
(in ₹ crore) |
Funds released (in ₹ crore) | Status |
| 1. | Improvement of Kakinada Anchorage Ports infrastructure in East Godavari district, Andhra Pradesh | Andhra Pradesh | 73.34 | 36.67 | 36.67 | Completed |
| 2 | Recycling/Reuse of Sewage Treated Water from Sewarage Infrastructure Development Corporation of goa Ltd (SIDCGL) located at KatemBaina, Goa | Goa | 3.18 | 3.18 | 3.02 | Completed |
| 3 | Removal of 2 Nos. Mooring of Spiral in the area of Cruise Berth – Mormugao, Goa | Goa | 13.87 | 6.94 | 6.94 | Completed |
| 4 | Installation of 3 MWp Solar Power Plant with Virtual Net Metering on Turnkey Basis at Murmugoa Port, Goa | Goa | 11.90 | 5.93 | 5.93 | Completed |
| 5 | Installation of Fire Fighting Equipment at Karwar Port, Karnataka | Karnataka | 18.21 | 9.10 | 8.65 | Completed |
| 6 | Refurbishment and Capacity enhancement of Coastal liquid terminal -COT and NTB at Cochin Port, Kerala | Kerala | 19.27 | 14.45 | 14.45 | Completed |
| 7 | Reconstruction of South Coal Berth at Cochin Port for handling chemicals, Kerala | Kerala | 19.30 | 10.55 | 10.55 | Completed |
| 8 | Construction of Third Chemical Berth at Pirpau, Mumbai Port, Maharashtra | Maharashtra | 161.00 | 140.46 | 140.46 | Completed |
| 9 | SCADA and PLC automation system at Marine Oil Terminal at Mumbai Port, Maharashtra | Maharashtra | 22.77 | 22.77 | 22.77 | Completed |
| 10 | Capital Dredging for Puducherry Port, Puducherry | Puducherry | 27.65 | 27.45 | 27.45 | Completed |
| 11 | Development and Operation of a full-fledged Truck Parking Terminal adjacent to NH7A opposite to Fisheries college at V. O. Chidambaranar Port | Tamil Nadu | 23.69 | 10.00 | 10.00 | Completed |
| 12 | Construction of Breakwater both in North and South side of entrance channel- Berth-1- Berth-2 and Capital Dredging at Cuddalore Port -From entrance channel till cargo berths | Tamil Nadu | 135.00 | 67.50 | 67.50 | Completed |
| 13 | Development of paved storage yard at Chennai Port for handling export cargo | Tamil Nadu | 51.46 | 25.73 | 25.73 | Completed |
| 14 | Construction of Bunker berth at Chennai Port | Tamil Nadu | 44.00 | 22.00 | 22.00 | Completed |
| 15 | Dredging the dock basin for coastal cargo berth at VOCPT -Dredging in front of dedicated coastal berth | Tamil Nadu | 98.00 | 20.89 | 20.89 | Completed |
| 16 | Development of Buffer Parking yard for Trailers / Trucks at the backup areas of Berth No. 24B(BD-II) in Chennai Port | Tamil Nadu | 49.06 | 39.42 | 39.42 | Completed |
| 17 | Design, Engineering & Construction for Rehabilitation of No.7, NSD Old Berth including Development of Backyard at N.S. Dock of KDS – SMP, Kolkata’ | West Bengal | 80.74 | 80.74 | 80.74 | Completed |
| 18 | Augmentation of Firefighting facilities at Berth no. 8 of Murmugoa Port | Goa | 17.76 | 8.88 | 7.10 | Under Implementation |
| 19 | Augmentation of Firefighting facilities at Pir Pau Terminal of Mumbai Port | Maharashtra | 52.69 | 26.34 | 25.03 | Under Implementation |
| 20 | Development of paved storage yard at marshalling yard and JD (east) back up area for handling EXIM cargoes at Chennai Port | Tamil Nadu | 45.90 | 22.95 | 4.51 | Under Implementation |
| 21 | Smart Lighting on Willingdon Island at Cochin Port | Kerala | 2.01 | 2.01 | 0.00 | Under Implementation |
| 22 | 2.3 MWp roof mounted grid connected solar photo voltaic power plant at Khidderpore Dock-II, SMPA | West Bengal | 30.70 | 15.35 | 3.07 | Under Implementation |
| 23 | Extension and improvement of loading platform of full rake line no. 8 and modification to railway infrastructure for handling two rakes at Murmugoa Port | Goa | 12.58 | 12.58 | 0.00 | Under Implementation |
| 24 | Revamping/upgradation of 6 (Six) roads in port operational areas of KDS under SMPA | West Bengal | 19.35 | 9.68 | 7.74 | Under Implementation |
This information was given by the Union Minister of Ports, Shipping, and Waterways, Sarbananda Sonowal, in a written reply to the Lok Sabha.